Client: Esfahan Steel mill Factory
Consultants: Esfahan Operation Dept.
Location: EsfahanProvince-CentralPartofIran
General Contractor: Kerman Tablo Co. KTC
C&I Contractor: Kerman Tablo Co. KTC
Status: Finished
Objective:
Replacement of conventional SCADA system of Esfahan steel mill Power distribution and production network with a new one Plant
Characteristics:
Esfahan steel mill power production and distribution network With the capacity of about 150MW in two steam power Plants,one gas Power plant, one 230kv, three 63kv,ten10.5 kV, Seventeen 6.3 kV station(s).(Totally 34 stations)
KTC Scope of work:
- design, manufacturing & installation of about one Thousand three (3) phase intelligent Transducers, harmony measurement system and event Recorder
- design, manufacturing & installation of 34 RTUs
- design, manufacturing & installation of a control center sothat all hardware components and computer network are redundant and each workstation connects to two monitors.